Saturday, March 14, 2026
spot_img

New Railway Track Commissioning in Odisha Registers Over 3.5 Times Increase; 2,150 km Commissioned During 2014–25 as Against 267 km in 2009–14

Ministry of Railways

azadi ka amrit mahotsav

New Railway Track Commissioning in Odisha Registers Over 3.5 Times Increase; 2,150 km Commissioned During 2014–25 as Against 267 km in 2009–14


226 Km of Khurda Road-Bolangir New Line Commissioned, All Seven Tunnels Excavated on Final 75-Km Daspalla-Purunakatak Section

57 Km of Salegaon-Budhapank 3rd and 4th Line Commissioned; 6 Major Bridges and 2 Stations Complete on Remaining 28 Km

Posted On: 13 MAR 2026 5:43PM by PIB Delhi

Railway has taken up infrastructure upgradation in Odisha in a big way.

Railway Budget:

Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Odisha is as under: 

Period

Outlay

2009-14

₹ 838 Cr./year

2025-26

₹ 10,599 Cr. (Nearly 13 times)

 

Track Construction:

The details of commissioning/laying of new track falling fully/partly in the State of Odisha during 2009-14 and 2014-25 is as under: 

Period

New Track Commissioned

Average Commissioning of new tracks per year

2009-14

267 Km

53 Km

2014-25

2,150 Km

195 Km

(More than 3.5 times)

 Project Sanctioned:

As on 01.04.2025, 49 projects (19 New Lines and 30 Doubling), of a total length of 4,010 Km, costing ₹ 67,496 crore, falling fully/partly in Odisha, are sanctioned, out of which 1,429 km length has been commissioned and an expenditure of ₹28,043 crore has been incurred upto March’ 2025. The summary is as under:-

Category

No of sanctioned Projects

Total Length

NL/GC/DL

(in Km)

Length Commissioned till Mar’25
 (in Km)

Total Exp upto Mar’25

(in Cr)

New Lines

19

1,544

256

6,270

Doubling/Multi-tracking

30

2,466

1,173

21,773

Total

49

4,010

1,429

28,043

 Recently Completed Projects:

Details of some of the recently completed projects falling fully/partly in Odisha are as under:

SN

Name of Project

Cost

(In Crores of ₹)

1

Daitari-Banspani New Line and Jakhapura-Haridaspur 3rd Line (179 Km)

1,317

2

Jharsuguda – Sardega New Line (50 Km)

1,598

3

Haridaspur-Paradeep New Line (82 Km)

2,397

4

Angul-Sukinda New Line (104 Km)

2,834

5

Champa-Jharsuguda 3rd Line (152 Km)

1,227

6

Sambalpur-Titlagarh Doubling (182 Km)

2,262

7

Rourkela-Jharsuguda 3rd Line (101 Km)

1,313

8

Banspani-Daitari-Tomka-Jakhapura Doubling (164 Km)

1,827

9

Sambalpur-Talcher Doubling (174 Km)

1,539

10

Raipur – Titlagarh Doubling (203 Km)

1,171

11

Jharsuguda-Sardega Doubling (50 Km)

3,200

 Ongoing Projects:

Further, some of the main projects falling fully/partly in Odisha which have been taken up are as under: 

SN

Name of Project

Total Cost
 (In Crores of ₹)

1

Junagarh-Nabarangpur New Line (116 Km)

2,865

2

Nabarangpur-JeyporeNew Line (41 Km)

748

3

Jeypore-Malkangiri New Line (130 Km)

2,344

4

Malkangiri – Pandurangapuram New Line (174 Km)

3,592

5

Buramara-Chakulia New Line (60 Km)

1,459

6

Gunupur-Therubali New Line (74 Km)

1,166

7

Puri – Konark New Line (32 Km)

492

8

Badampahar-Kendujhargarh New Line (82 Km)

1,876

9

Bangriposi-Gorumahisani New Line (86 Km)

2,269

10

Bargarh Road-Nawapara Road New Line     (138 Km)

2,622

11

Vizianagram-Titlagarh 3rd Line (265 Km)

6,996

12

Jarapada- Budhapank 3rd& 4th Line with flyover at Talcher (101 Km)

810

13

Budhapank- Salegaon via Rajatgarh 3rd& 4th Line (170 Km)

2,023

14

Nergundi – Vizianagaram 3rd Line (385 Km)

4,963

15

Kottavalasa-Koraput Doubling (189 Km)

2,500

16

Koraput-Singapur Road Doubling (165 Km)

2,362

17

Jagdalpur-Koraput Doubling (107 Km)

1,547

18

Jharsuguda-Bilaspur 4th line (206 Km)

2,596

19

Bondamunda-Ranchi Doubling (159 Km)

3,029

20

Narayangarh-Bhadrak 3rd line (153 Km)

2,136

21

Bhadrak-Nergundi 3rd Line (92 Km)

1,284

 The progress of some of the major projects is as under:

1. Khurda Road-Bolangir (301 Km) new line: The latest cost of the project is ₹5,089 crore. Expenditure of ₹4,311 crore has been incurred on this project upto March, 2025. An outlay of ₹1938 crore has also been provided in the financial year 2025-26. Status of project is as under:-

  • Khurda Road – Daspalla (106 Km) : Commissioned
  • Daspalla – Purunakatak (75 Km) : Works have been taken up.
  • Purunakatak – Bolangir (120 Km) : Commissioned

Status of Daspalla – Purunakatak (75 km) is as under:- 

SN

Activity

Scope

Status

1

Tunnel

7 nos (11.96 Km)

6 nos completed (7.7 Km).Works taken up in balance 1 tunnel

2

Important Bridge

5

All completed

3

Station Building

5

Works have been taken up

 2. Construction of 3rd and 4th line between Salegaon- Budhapank(85 Rkm): The work has been taken up. Status is as below:-

  • Salegaon – Rajathgarh (23 Km) : Commissioned
  • Rajathgarh – Dhenkanal (20 Km) : Land acquisition & forest land diversion completed. 4 major bridges completed. Balance work has been taken up.
  • Dhenkanal – Meramundali (34 Km) : Commissioned
  • Meramundali – Budhapank (8 Km) : Land acquisition & forest land diversion completed. 2major bridges and 2 stations completed. Balance work has been taken up.

 Sanction of any railway project depends upon many parameters/factors which include the following:

  • Anticipated traffic projections and Remunerativeness of the proposed route
  • First and last mile connectivity provided by the project
  • Connection of missing links and providing additional route
  • Augmentation of congested/saturated lines
  • Demands raised by State Governments/Central Ministries/Public representatives,
  • Railway’s operational requirements
  • Socio-economic considerations
  • Overall availability of funds

 Completion of Railway project/s depends on various factors which include the following:

  • Land acquisition
  • Forest clearance
  • Shifting of infringing utilities
  • Statutory clearances from various authorities
  • Geological and topographical conditions of area
  • Law and order situation in the area of project site
  • Number of working months in a year for particular project site etc.

All these factors affect the completion time and cost of the project/s.

Presently, Bhubaneswar–Rayagada–Jeypore–Koraput sector is being served by the daily service of 18447/18448 Bhubaneswar-Jagdalpur Hirakhand Express. Moreover, Koraput is connected to Kottavalasa by 03 pairs of train services while Kottavalasa is further connected to Bhubaneswar by 06 pairs of train services. These train services are listed below:

Trains serving Koraput-Kottavalasa sector:

SN

Train No & Name

1

18515/18516 Kirandul – Visakhapatnam Express

2

58501/58502 Kirandul – Visakhapatnam Passenger

3

58537/58538 Koraput – Visakhapatnam Passenger

 Trains serving Kottavalasa- Bhubaneswar sector:

SN

Train No & Name

1

16107/16108 Tambaram – Santragachi Amrit Bharat Express

2

16597/16598 SMVT Bengaluru – Alipurduar Amrit Bharat Express

3

16523/16524 SMVT Bengaluru – Balurghat Express

4

16223/16224 SMVT Bengaluru – Radhikapur Express

5

17015/17016 Secunderabad – Bhubaneswar Visakha Express

6

18045/18046 Charlapalli – Shalimar East Coast Express

This information was provided by the Union Minister for Railways, Information & Broadcasting and Electronics & Information Technology, Shri Ashwini Vaishnaw, in a reply to a question in Rajya Sabha today.

*****

Dharmendra Tewari/ Nayan Solanki/ Manik Sharma

(Release ID: 2239725) Visitor Counter : 63

Source Link

The NewsHourhttps://www.thenewshour.org
The News Hour – Online News Media, providing the Latest and Credible news for Lakhs of people in India as well as abroad. The Online News Media provides the Latest & Real-time news on Business, Automobiles, Latest Useful Top News, Food & Travel, Health, Education, Entertainment, Agriculture & Environment, Fashion & Lifestyle, Sports, Events…etc. The News Hour – Online News Media, has always brought useful news and analysis to the doorstep of the Industry through its exclusive content, updates, and expertise from industry leaders through its Online News Website. The News Hour – Online News Media coverage will help in reaching you to the target customers/buyers. This is the right time for Companies to Turn Disruptions into Opportunities by being part of this online coverage. The News Hour Provides Advertisers with a strong Digital Platform to reach lakhs of people in India as well as abroad.

Related Articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -spot_img

Top News

LATEST ARTICLES

BIZ NEWS